Tender winning company has already started the construction of main gas pipeline aimed to supply natural gas to the Akhalkalaki region

16 September, 2007
Tender winning company has already started the construction of a 6 km long section of the main gas pipeline aimed to supply natural gas to the Akhalkalaki region. Construction work is being carried out by Gas Transportation Company alongwith its sub-contractor New Energy.

2.5 km long trench has already been excavated and polyethylene pipes have been lowered on 1, 8 km. Construction works are scheduled to finish early in December. The contract also envisages installation of two distribution points in order to supply 7 villages of the Akhalkalaki region with natural gas.