About 80% of Construction Works on Rustavi-Sagarejo Section Have Been Completed

27 August, 2014
Construction of DN 300 Rustavi-Sagarejo 25 km section of the Kakheti branch of the main gas pipeline is in progress. Currently 79% of works have already been completed.

Construction works started in February 2014, and according to the contract are expected to be completed in September this year. Works are being carried out by a tender-winning company- Komfortmsheni XXI. The total cost of the project makes up 5 194 207 GEL..

The completion of the Rustavi-Sagarejo DN 300 pipeline project will ensure secure supply of natural gas to the Kakheti region via so called ‘ring type’ system.