Works Underway on "North Caucasus-Transcaucasia" and "Vladikavkaz-Tbilisi" Main Gas Pipelines
20 October, 2025
Ekaterine Sisauri, General Director of GOGC, accompanied by Shalva Kiknavelidze, Technical Director, inspected the ongoing works in Dusheti Municipality. The focus of the inspection was the DN1200 mm "North Caucasus-Transcaucasia" and the DN700 mm "Vladikavkaz-Tbilisi" main gas pipelines.
Due to the construction of a new road and bridges by the Roads Department of Georgia, the pipeline is changing its location at thirteen different places across seven sections, guaranteeing that its consistent and proper functioning remains uninterrupted.
Despite the challenging terrain, the contractor company is executing all works in strict accordance with the technical plan developed by GOGC and in full compliance with all international standards.