Vnipitransgas completed construction works on the Navtlugi-Saguramo 50km section of the pipeline

20 February, 2009
The Ukrainian Engineering and Production Enterprise Vnipitransgas completed construction works on the Navtlugi-Saguramo 50km section of the main gas pipeline.

Technical department has already received a 15 volume document, containing the recommendations of Georgian experts.

Soon field works will start on the Navtlugi-Saguramo 50km section of the main gas pipeline. These will include the process of obtaining authorization for the construction as well as the selection of the company that will carry out construction works on the site. The construction works are planned to complete in 2010.

The Navtlughi-Saguramo 50km section of the main gas pipeline is part of the Saguramo-TsiteliKhidi project, phase II. Under phase I, Gardabani–Navtlughi 30 km section has been constructed.